Project Name
|
Description
|
|
|
|
Services Provided
|
Client
|
Country
|
Image
|
Engineering of Power Generation and Distribution System at Norpetco Field |
Upgrading of Electrical Power Supply to Achieve a More Reliable and Sustainable Service by Dividing Scope of Work into Six Clusters Headed as Abrar, Abrar South, Ferdaus, Ganna, Sidra and Rawda |
2013 |
2015 |
10 |
Feasibility Study, Study Report, Tender Document, Detailed Design, Master Plan, Planning, Forecast |
NORPETCO - North Baharya Petroleum Company |
Egypt |
|
Consultancy Services for Design Stability of Piping System in Pump Room - The Development of South Shamkha Infrastructure, Lot-1 (Cont No. 2011/61) - Pipe Stress Analysis |
Design Stability of Piping System in Pump Room - The Development Of South Shamkha Infrastructure, Lot-1 - Pipe Stress Analysis |
2014 |
2015 |
0 |
Hydraulic Studies (Steady State, Un-Steady State), Hydraulic Model, Detailed Design |
Federal Electricity & Water Authority FEWA |
United Arab Emirates UAE |
No Image
|
Seawater Intake Culvert Concrete Slab Repair and Impressed Cathodic Protection System Inspection and Recommendation in Al Ghubrah Plant |
Concrete Structures in Many of the Power and Desalination Plants Had Suffered Disintegration of Its Concrete Surface, Deterioration of Concrete, Rusting of Reinforcement and Crack Along and Across the Reinforcement |
2013 |
2015 |
2 |
Study Report, Prequalification of Contractors, Tender Document, Bid Evaluation, Assistance to Prepare Contract, Construction Management & Supervision, Planning, Forecast |
Al Ghubrah Power & Desalination Co |
Sultanate Of Oman |
No Image
|
Design of Training Center and Mosque at P&G s New Plant |
Prepare and Carrying Out the Construction Design Package Design Calculation, Detailed Drawings, Bill of Quantities and Specifications For The Landscaping and Layout of the External Works and All Architectural Design |
2014 |
2015 |
1.2 |
Detailed Design, Topographical Survey |
PROCTER and GAMBLE |
Egypt |
No Image
|
Calculations of Energy Cost Saving by Using Led Lighting |
ETG Company – Represented by Eng. Islam Gabr – Offered The Calculation of Energy Cost Saving by Replacing the Traditional Lighting by Led Lighting |
2015 |
2015 |
1 |
Revise The Calculations Made by Etg for Saving of Electrical Energy by Using Led Lighting the Financial Include Fixer Cost of Aperatnity |
Arab Company for Projects and Urban Development |
Egypt |
No Image
|
Transmission Pipeline Within City and Industrial Area – Ajman |
Transmission Pipeline Within City and Industrial Area – Ajman |
2014 |
2015 |
0.5 |
Hydraulic Studies (Steady State, Un-Steady State), Hydraulic Model |
Federal Electricity & Water Authority FEWA |
United Arab Emirates UAE |
No Image
|
Technical Evaluation Report About Advanced Meter Infrastructure (Ami) For Madinaty Project. |
Review The Technical Submission of Supplier (Golden Power & Having Co.) And Evaluation the Preliminary Offer Against International Standard. |
2014 |
2015 |
0.5 |
Evaluation Report, Data Collection, Review of Current Specification |
Madinaty Electromechanical Power Company (MEPC) |
Egypt |
No Image
|
Concrete Testing and Structural Integrity to Mv&Lv Switchgear Room Building at Elsokhna Power Plant |
Suez Golf Power Plant at Km 52 Suez City Ain Soukhna Structural Integrity Report |
2015 |
2015 |
0.3 |
Soil Investigation, Structural Integrity Report |
Powertek Energy SDN BHD |
Egypt |
No Image
|
Consultancy Services for Supervision of Construction of Sea Water Pipeline Construction from Phase 3/Phase 1 Diversion Point and Extend Towards Phase 2 Settling Basin |
Consultancy Services for Supervision of Construction of Sea Water Pipeline Construction from Phase 3/Phase 1 Diversion Point and Extend Towards Phase 2 Settling Basin |
2013 |
2015 |
0 |
Site Supervision, Inspection and Site Visits |
Ghubrah Power & Desalination Company SAOC |
Sultanate Of Oman |
No Image
|
Consultancy services for soil settlement investigation at al taweelah B plant |
Sea water pumping station, distiller unit and power unit foundation, pipe rack settlement of fills & soil movement for civil structure/pipes for data collection, samples collection, measurements, analysis of samples and measurements, results analysis, technical recommendations, design & specification preparation for remedial works in determined locations at altaweelah site
|
2013 |
2014 |
1500 |
studying different possible causes of movement and distress, data collection, site survey and site investigation, technical assessment
|
Asia Gulf Power Services Company Limited |
United Arab Emirates UAE |
|
Number of projects: 279
|