Project Name
|
Description
|
|
|
|
Services Provided
|
Client
|
Country
|
Image
|
General Technical and Financial Specification for Construction of open Advanced Metering Infrastructure ( Ami) , Management and Billing System |
Design and Installation, Testing, Operation and Warrantee Open Advanced Metering Infrastructure, Management and Billing System for Smart Water and Electric Meters for Madinaty Project |
2018 |
2023 |
5 |
Evaluation Report, Preparing Recommendation Report, Preparing Technical Specification for The Construction Of Open Advanced Metering Infrastructure, Management And Billing System, Preparing Terms Of Reference, Boq, Evaluation Received Offers, Reply To Clarification And Attending Clarification Meeting With Tenders, Assisting Madinaty To Award Contract To Successful Tenderer, Recommend The Successful Tenderer |
Arab Company for Projects and Urban Development |
Egypt |
|
Consultancy Services for Supply and Installation of Electromagnetic Bulk Meters with Control Valves and Actuators On Existing Bulk Connection Points in Abu Dhabi Island (Consultancy Agreement D-106743). |
Consultancy Services for Design and Site Supervision for Providing Monitoring and Control Facilities at Specified Bulk Connection Points, Smp and Interface Locations Within the Abu Dhabi Island Distribution Network & Surrounding Islands. |
2018 |
2023 |
0 |
Investigation, Studies & Design, Final Design & Technical Tender Documents Final Contractor Tender Documents, Tendering, Evaluation & Awarding Construction Supervision, Field Supervision During Warranty Period |
ABU DHABI DISTRIBUTION COMPANY |
United Arab Emirates UAE |
|
Consultancy Service for Replacement/Reinforcement of Prms Phase 1, In Central Region of Abu Dhabi (Consultancy Agreement No. D-107307). |
Consultancy Services for Replacement of Existing Water Distribution Network of Approximately 29 Km with All Associated Civil Work for Prm’s in Central Region. |
2018 |
2023 |
0 |
Studies, Review, Of Existing PDR and DDR and Prepare New DDR and Tender Documents, Preparation of Draft and Final Contractor’s Tender Document (Including Drawings, BQQ, Specifications, And Technical Data Etc.), Assistance During Contractors’ Tendering Period Including Analysis and Evaluation Reports, And Preparation of Final Contract Documents, Site Supervision Services During Construction Period Site Supervision Services During Warranty Period |
ABU DHABI DISTRIBUTION COMPANY |
United Arab Emirates UAE |
|
Consultancy Services for Supply and Installation of Valve Actuators On Selected System Valves in Abu Dhabi Island (Consultancy Agreement D-106742). |
Consultancy Services For Design And Site Supervision For Providing Monitoring & Control Facilities For Selected Isolation Valves In The Abu Dhabi Central Region Distribution Network. |
2018 |
2023 |
0 |
Studies, Surveys, Detailed Design Report, And Contractor’s Tender Document, Assistance During The Contractors Tendering Period Including Submission Of Analysis And Evaluation Reports And Preparation Of Final Contract Documents For The Works, Site Supervision Services During The Construction Period, Field Supervision During Warranty Period. |
Abu Dhabi Distribution Company |
United Arab Emirates UAE |
|
The first egyptian Nuclear power plant (NPPA) |
4 X 1000 MW Nuclear Power Plants |
2009 |
2022 |
8000 |
TBD |
Egyptian Nuclear Power Plants Authority |
Egypt |
|
CONSULTANCY SERVICES FOR SAIH AL KHAIRAT GS ALONG WITH OVERHEAD LINE FROM THUMRAIT GS TO SAIH AL KHAIRAT |
125MVA, 132/33KV GRID STATION
ALONG WITH OHTL. |
2019 |
2022 |
7 |
DESIGN - TENDERING
EVALUATION REPORT - DESIGN
REVIEW - CONSTRUCTION
SUPERVISION - GUARANTEE
PERIOD |
OMAN ELECTRICITY TRANSMISSION CO. |
Sultanate Of Oman |
|
DESK STUDY OF WASTEWATER EVAPORATION PONDS AT NEW CAPITAL POWER PLANT |
PROVIDING EVAPORATION ROLE ,
AERATION SYSTEM , POND
CLEANING |
2020 |
2022 |
0 |
REVIEW , FEASIBILITY STUDY ,
CONCEPT DESIGN , DETAILED
DESIGN , TENDER SPECIFICATION
, SUPERVISION |
EGYPTIAN ELECTRICITY HOLDING CO. |
Egypt |
|
INTRO GROUP - NCMP - CHP – PLANT |
10MW CHP GAS TURBINE
GENERATOR , HRSG AND
AUXILIARIES , CIVIL WORKS |
2021 |
2022 |
20 |
PREPARING DESIGN , TENDER
PREPARATION , EVALUATION OF
BIDDERS TILL AWARDING
CONTRACT FOR CHP PLANT
(INCLUDING GAS TIMELINE ) HEAT
RECOVERING STEAM
GENERATOR , BLACK START
DIESEL GENERATOR AND THEIR
AUXILIARIES
PAST CONTRACT WORK REVIEW
OF CONTRACTOR ,
SPECIFICATION AND DRAWING
SITE SUPERVISION , ATTENDING
LOCAL FACTORY , INSPECTION ,
COMMISSIONING , HANDING OVER
TO OWNER , PERFORMANCE
TEST , GUARANTEE , PREPARING
SPARE PARTS ACTIVITIES TILL
FINAL ACCEPTANCE TEST |
INTRO UTILITIES SAE |
Egypt |
|
INTRO GROUP – NCMP CCHP PLANT |
GAS ENGINE , HRSG AND COOLING
SYSTEM |
2021 |
2022 |
0 |
PREPARING DESIGN , TENDER
PREPARATION , EVALUATION OF
BIDDERS TILL AWARDING
CONTRACT FOR CHP PLANT
(INCLUDING GAS TIMELINE ) HEAT
RECOVERING STEAM
GENERATOR , BLACK START
DIESEL GENERATOR AND THEIR
AUXILIARIES
PAST CONTRACT WORK REVIEW
OF CONTRACTOR ,
SPECIFICATION AND DRAWING
SITE SUPERVISION , ATTENDING
LOCAL FACTORY , INSPECTION ,
COMMISSIONING , HANDING OVER
TO OWNER , PERFORMANCE TEST , GUARANTEE , PREPARING
SPARE PARTS ACTIVITIES TILL
FINAL ACCEPTANCE TEST |
INTRO UTILITIES SAE |
Egypt |
|
CONSULTANCY SERVICES FOR DESIGN VERIFICATION, OBTAINING NOC AND BUILDING PERMIT FOR ADDC PROJECT NO. D-109056 |
DESIGN VERIFICATION, OBTAINING
NOC AND BUILDING PERMIT |
2021 |
2022 |
0 |
DESIGN VERIFICATION &
OBTAINING NOCS’ |
ABU DHABI MAINTENANCE AND CONSTRUCTION |
United Arab Emirates UAE |
No Image
|
Number of projects: 279
|