Project Name
|
Description
|
|
|
|
Services Provided
|
Client
|
Country
|
Image
|
MIRFA Sea Water Intake |
Dredging & Reclamation for Sea Water Intake Channel |
1993 |
1994 |
50 |
Engineering Design, Preparation of Tender Documents, Bids Evaluation, Post Contract Duties including supervision of construction, commissioning and guarantee period.
|
Department of Public Works |
United Arab Emirates UAE |
|
RO Plant Capacity 40000 M3/D Phase 1 20000 M3/D at Port Said |
Carrying Out Ro Desalination Plant Capacity 20000 M3/D Extendable to 40000 M3/D Including the Hydraulic /Marine Studies, Environmental Study |
2017 |
2019 |
50 |
Design Review Of Electro Mechanical Design /Drawings, Hydraulic Studies (Steady State, Un-Steady State), Hydraulic Model, Design Of Intake And Outfall Pipelines, Environmental Study |
National Organization for Potable Water and Sanitary Drainage(Nopwasd) |
Egypt |
|
Addition of 6th Desalination Unit at Ghubrah Power and Desalination Plant |
6/7 MIGPD Desalination Unit, complete with all auxiliaries and ancillaries. |
1997 |
2001 |
52 |
Engineering Design, Preparation of Tender Documents, Bids Evaluation, Post Contract duties including supervision of Construction commissioning and guarantee period.. The project included different financial options for lease and BOOT |
Ministry of Electricity and Water, Muscat, Sultanate of Oman. |
Sultanate Of Oman |
|
Addition of Desalination Units No. 9 and 10 at Umm Al Nar Power and Desalination Plant |
2x3.5 MIGPD TVC Desalination Units using extraction steam from condensing turbines complete with all auxiliaries and ancillaries. |
1997 |
2000 |
55 |
Engineering Design, Preparation of Tender Documents, Bids Evaluation. |
Water & Electricity Department, Government of Abu Dhabi |
United Arab Emirates UAE |
|
Sitra Power & Desalination Plant Extension |
35.4 MW ISO rating gas turbine & 5/6 MIGPD desalination. plant, one Waste Heat Recovery Boiler of 80 ton/hr and one dual firing aux. boiler of 160 ton/hr. Seawater intake of 15000m3/hr complete with settling basin, chemical treatment and hypochlorination plant. |
1981 |
1985 |
55 |
Engineering Design, Preparation of Tender Documents, Bids Evaluation (of nominated Tenderer by the Client), Post Contract duties including Supervision of Construction and Commissioning. |
Water and Electricity Department, Abu Dhabi, End user: WED, Bahrain. |
Bahrain |
|
RO Desalination Plant of 25000 M3/D at hurghada |
Design Review & Supervision of Two Seawater RO Desalination Plant at Hurghada of Capacity 5 MIGD SWRO 20,000 M3/D + 5000 M3/D |
2010 |
2012 |
55 |
Bid Evaluation, Assistance to Prepare Contract, Construction Management & Supervision, Design Review, Attending Manufactures Tests, Commissioning |
National Orgnization for Potable Water And Sanitary Drainage(NOPWASD) |
Egypt |
|
Study The Technical Data of 3 Phase Electric Meter by Manas |
Checking The Technical Inspection Data Prepared by “National Institute for Standard"
- Submit Technical Report About the Study of 3 Phase Meter
|
2015 |
2015 |
55 |
Test Of Accuracy ,Test Of Electrical Recommendation ,Test Of Insulation ,Conclusion And Recommendation, Disturbance Of Long Duration |
Madinaty Electromechanical Power Company (MEPC) |
Egypt |
No Image
|
Replacement of gas chlorination systems at various pumping station |
Installation of 48 Nos. sodium hypochlorite generation plants of different capacity in all of the pumping stations belongs to Abu Dhabi Water & Electricity Authority,Automatic control system for Hypochlorite generation including PLC, UDU and SCADA Systems.
|
2003 |
2007 |
55.2 |
Preparation of study and design report, tender documents, bids evaluation, site supervision, commissioning and supervision of guarantee. |
Abu Dhabi Water and Electricity Authority |
United Arab Emirates UAE |
|
RO PLANT CAPACITY 45,000 M3/D AT SIR BANI YAS ISLAND ABU DHABI |
DESIGN OF ONSHORE SEAWATER
INTAKE AND OUTFALL
STRUCTURES , OFFSHORE
SEAWATER INTAKE TOWER,
ONSHORE OUTFALL PIPELINE (
Ø=1100MM) , OUTFALL WEIR ON
SHORELINE, AND ONSHORE &
OFFSHORE SEAWATER INTAKE
PIPELINES (2NOS Ø 900 MM AND
L≈≈300M) |
2020 |
2021 |
58 |
ORASCOM
CONSTRUCTION
INDUSTRIALS |
|
United Arab Emirates UAE |
|
Construction of Integrated Simple Cycle Gas Turbine Power Plant at SUR |
Construction of a New Power plant with 2X30 or 3X20 MW Simple Cycle gas turbine at Birbuira site in SUR integrated with existing MEW network at SUR
|
1998 |
1998 |
60 |
Preparing Study Report and Design Report
|
Public Authority for Electricity and Water PAEW |
Sultanate Of Oman |
|
Number of projects: 279
|