Sitra Power & Desalination Plant Extension |
|
Description: |
35.4 MW ISO rating gas turbine & 5/6 MIGPD desalination. plant, one Waste Heat Recovery Boiler of 80 ton/hr and one dual firing aux. boiler of 160 ton/hr. Seawater intake of 15000m3/hr complete with settling basin, chemical treatment and hypochlorination plant. |
Start Date: |
1981 |
Complation Date: |
1985 |
Cost: |
55 million US $ |
Services Provided: |
Engineering Design, Preparation of Tender Documents, Bids Evaluation (of nominated Tenderer by the Client), Post Contract duties including Supervision of Construction and Commissioning. |
|
|