Ben Ban Ohtl (Solar Project) |
|
Description: |
Transmission of The Solar Electric Power from The Solar Plots (39 Plots with Total Power of 1850 Mw) At Benban Area – Aswan – Upper Egypt Electricity Area to Their Located Step Up Substations (4 Nos) 22/22/220 Kv to Be Connected to The National Grid (220 Kv Level) At The Same Area. By Using Ohtl Instead of Cable Connection. |
Start Date: |
2016 |
Complation Date: |
2016 |
Cost: |
23 million US $ |
Services Provided: |
PRELIMINARY EVALUATION OF OVERHEAD LINE POLES REQUIRED FROM PLOTS TO THE SUBSTATIONS,DETAILED DESIGN FOR CIVIL WORKS AND POLES , PLANNING , FORECAST |
|
|