Smart Water Network for Madinaty Project |
|
Description: |
Phase I: Data Transfer To Consortium To Prepare The Hydraulic Study For All Madinaty Phases .
-Detailed Engineering Of The System Including Scada System For Automatic Control, Prepare BOQ Of Main Equipment
Phase Ii : Preparing Planning Program Of Installation Of Equipment, Follow Up Installation, Testing, Of All Equipment Till Taking Over The Project.
|
Start Date: |
2015 |
Complation Date: |
2018 |
Cost: |
14 million US $ |
Services Provided: |
Data Collection, Hydraulic Studies (Steady State, Un-Steady State), Review Of Current Specification, Site Supervision, Testing, Commissioning Till The Taking Over Of Project, Engineering By Consortium, Review Of BOQ, |
|
|