Al Kamil Power Plant |
|
Description: |
3x123MW ISO GE frame 9E gas turbines, 2x600m3 fuel oil tanks, All associated electro-mechanical works, All associated civil works, The project is BOO Basis. |
Start Date: |
2001 |
Complation Date: |
2003 |
Cost: |
120 million US $ |
Services Provided: |
Detailed Design for Mechanical, Civil, Electrical, I&C, Gas turbine foundation design and interfaces, Sub-vendor and subcontractor nomination and evaluation, Amendments due to site changes, troubleshooting during construction. |
|
|