Chlorination System & Associated Works in the Sharqiya Region |
Water Sterilization – Dis-infection by using Chlorine Dioxide in a Sharqiya Region for 20 water wells at 8 different location |
2004 |
2005 |
1.5 |
Design review & site supervision |
Ministry of Electricity and Water, Sultanate of Oman |
Sultanate Of Oman |
|
Construction and Maintenance of Totalized Flow Valve Control for Local Farms in Taweelah, Bahia & Rahba |
Construction and Maintenance of Totalized Flow Valve Control for Local Farms in Taweelah, Bahia & Rahba – Abu Dhabi Emirate including construction, commissioning and guarantee of 2 pumping stations (3 x 135 m3 /hr) each and rehabilitation of one similar existing pumping station. |
2003 |
2005 |
1.9 |
Studies, Design, Preparation of Tender Documents, Tender Analysis, Post-contract duties including supervision of construction and commissioning, and guarantee period. |
Abu Dhabi Municipality |
United Arab Emirates UAE |
|
Upgrading of Mirfa, Madinat Zayed, Water Transmission Scheme |
DN 900mm pipeline (DI) from Mirfa to Madinate Zayed (70 km),Two pumps in existing pumping stations, MCC’s, Power and control tanks 2x2 MG,DN 900 pipeline (DI) room Madinate Zayed to Mazaira,2x6 MIG + 1x5 MIG concrete reservoirs,Investigation and conversion to VFD of existing motors,Automatic control system. |
2004 |
2009 |
75 |
Investigation, concept and detailed design, all surveys, tendering, site supervision and warranty follow up |
Abu Dhabi Water and Electricity Authority (ADWEA) |
United Arab Emirates UAE |
|
Ghayathi & Hamra Military Camp |
DN 600 mm pipeline (40 km) from DN 1600 mm pipeline, interconnection to filling station and network, DN 300 mm pipeline (3 km) from DN 1000 mm pipeline, all instructions and control, elevated tank 100,000 gallons x 30 m and associated control systems. |
2004 |
2007 |
11 |
Concept and preliminary design, detailed and tender documents, tendering, evaluation and award, construction supervision, warranty period filed supervision. |
Abu Dhabi Water and Electricity Authority (ADWEA) |
United Arab Emirates UAE |
|
Drilling 100 Wells, at Al Yahr – Al Ain |
Drilling 100 Wells, Dept. 1000 Ft. per Well with Casing and Screen for Full Depth at Al Yahr – Al Ain |
2004 |
2005 |
3.5 |
Post-contract duties including supervision of construction and commissioning |
Agriculture Dept. & Livestock, Al Ain – U.A.E. |
United Arab Emirates UAE |
|
Drilling 150 Wells, at Seih Al-Rahil - Al Ain City |
Drilling 70 Wells with Pumps inside Al Ain City |
2004 |
2005 |
4 |
Post-contract duties including supervision of construction and commissioning |
Agriculture Dept. & Livestock, Al Ain – U.A.E |
United Arab Emirates UAE |
|
Drilling 100 Wells at Al Anja, Al Ain |
Drilling 100 Wells, Dept. 1000 Ft. per Well with Casing and Screen for Full Depth at Al Anja –Al Ain |
2003 |
2005 |
3.52 |
Post-contract duties including supervision of construction and commissioning |
Agriculture Dept. & Livestock, Al Ain – U.A.E. |
United Arab Emirates UAE |
|
Water Distribution Network to New Industrial City in Mussafah |
Construction of Water Distribution Network to Industrial City in Mussafah, including all connections and fittings required to supply water to industrial consumers. |
2002 |
2006 |
4.3 |
Preparation of design report, tender documents, bids evaluation, post contract duties including site supervision of construction and commissioning |
Abu Dhabi Water and Electricity Authority |
United Arab Emirates UAE |
|
Replacement of gas chlorination systems at various pumping station |
Installation of 48 Nos. sodium hypochlorite generation plants of different capacity in all of the pumping stations belongs to Abu Dhabi Water & Electricity Authority,Automatic control system for Hypochlorite generation including PLC, UDU and SCADA Systems.
|
2003 |
2007 |
55.2 |
Preparation of study and design report, tender documents, bids evaluation, site supervision, commissioning and supervision of guarantee. |
Abu Dhabi Water and Electricity Authority |
United Arab Emirates UAE |
|
Installation of Sub-Pumps Bida Yamra |
Installation and maintenance of 100 Nos-Elect. Sub-pumps including:diesel generator with its accessories,telemetry system,transformer and feeder piller |
2002 |
2006 |
2.25 |
Preparation of Design Report, Tender Documents, Bids evaluation, post contract duties including supervision of construction and commissioning |
Abu Dhabi Municipality UAE |
United Arab Emirates UAE |
|