Concrete Repair - Complete Site Survey for Cracked Concrete Structure at Suez Gulf Power Plant - Al Ain Al Sokhna SGP |
Complete Site Survey & Treatment Study for Cracked Concrete at Suez Gulf Power Plant Al Ain Al Sokhna |
2015 |
2015 |
757 |
Geo-Technical Report, Study Report, Topographical Survey |
Powertek Energy SDN BHD |
Egypt |
|
Sidi Krir Sea Water Intake |
Sea Water Intake Pit Level Depression & Effect On Cooling Water Capacity Flow. |
2015 |
2015 |
757 |
Site Survey, Data Collection for Cooling Water, Hydraulic Model, Technical Report, Study Report |
Powertek Energy SDN BHD |
Egypt |
|
Study For Repeated Damage Of Chlorine Sw Intake Injection Lines At Sidi Krir Power Plant |
Carrying Out a Full Assessment of the Repeated Damage to The Rc Sw Intake Chlorine Injection Pipes, Determine The Possible Root Cause(S) Of The Repeated Damage, Recommend The Possible Solution in Details. |
2015 |
2015 |
757 |
Design Review, Geo-Technical Report, Review of Current Specification, Soil Investigation, Topographical Survey, Study Report |
Powertek Energy SDN BHD |
Egypt |
No Image
|
El-Ameria new gas turbine power plant 3X63 MW ISO rating |
Interconnection with The 220kv Network Through The 220/66/11kv - 2x125mva S/S Consists of Three Gas Turbine 33mw Site Rating, 220kv Gis Switchgear, 66kv Ais Indoor Switchgear Both Double Bus Bar One Breaker Scheme and Two Main 125 Mva, 220/66/11 Kv Transformers |
2012 |
2015 |
167 |
Feasibility Study, Study Report, Concept Design, Prequalification of Contractors, Tender Document, Bid Evaluation, Assistance to Prepare Contract, Construction Management & Supervision, Attending Manufactures Tests, Commissioning, Guarantee Supervision |
Egyptian Petrochemicals Co. |
Egypt |
No Image
|
Updating and Standardizing the Requirements for Smart Network and Metering System |
Technical Evaluation Report for Proposals Submitted from Tenderers for Implementation of Updating Process to The Smart Network in Madinaty |
2015 |
2015 |
151 |
Tender Document, Review of Current Specification, Bid Evaluation, Technical Report |
Arab Company for Projects and Urban Development |
Egypt |
No Image
|
consultancy service for well drilling |
Construction Site Supervision Drilling And Maintenance Of Water Wells And Installation Of Casing And Screen To The Full Completed Depth In The Eastern & Western Region |
2012 |
2015 |
123 |
Study Report, Concept Design, Review of Current Specification, Construction Management & Supervision, Design Review, Guarantee Supervision, |
Abu Dhabi Food Control Authority |
United Arab Emirates UAE |
|
The Development of South Shamkha Infrastructure Lot 1 |
Construction of 2 New Pump Stations at South of Shamkha & 200 Km Piplines Ranging from 800 Mm to 100 Mm |
2014 |
2015 |
117 |
Surge Analysis, Pipe Street Analysis, Surge Vessel Foundation Design |
MUSANDAH |
United Arab Emirates UAE |
|
Consultancy Services of Supervision for Civil Construction Works |
Providing Civil Engineering Supervisory Staff |
2013 |
2015 |
114 |
Coordination with The Civil Engineering Works., Construction Management & Supervision, Guarantee Supervision |
Mazoon Electricity Company |
Sultanate Of Oman |
|
Study The Technical Data of 3 Phase Electric Meter by Manas |
Checking The Technical Inspection Data Prepared by “National Institute for Standard"
- Submit Technical Report About the Study of 3 Phase Meter
|
2015 |
2015 |
55 |
Test Of Accuracy ,Test Of Electrical Recommendation ,Test Of Insulation ,Conclusion And Recommendation, Disturbance Of Long Duration |
Madinaty Electromechanical Power Company (MEPC) |
Egypt |
No Image
|
Technical and Financial Evaluation to Extend Life Time of Midelec Power Station Turbines (LTE) |
Technical and Financial Evaluation of Siemens Co Offer to Extend A Life Time Gt11 & Gt21 Turbines(LTE) |
2015 |
2015 |
43 |
Life Time Extension Report (LTE) |
MIDELEC |
Egypt |
|