Project Name
|
Description
|
|
|
|
Services Provided
|
Client
|
Country
|
Image
|
Madinaty Irrigation Networks |
Automatic Irrigation Networks for different areas in Madinaty |
2010 |
2010 |
0.2 |
Technical & Financial Evaluation |
Arab Company for Projects and Urban Development |
Egypt |
|
Desalination of Ground Water In Madinaty |
Geophysical study(Electro potential & Exploratory Wells) to determine quantity & quality of ground water, well drilling, testing & drilling of productive wells including deep well pumps, water treatment including desalination of brackish water. |
2008 |
2011 |
4 |
Feasibility Study, Geophysical Survey, Project Management, Study Report, Concept Design, Prequalification of Contractors,Topographical Survey, Tender Document, Bid Evaluation, Assistance to Prepare Contract, Construction Supervision and Guarantee Follow up. |
Arab Company for Projects and Urban Development |
Egypt |
|
Wastewater Tratments Plant in Madinaty |
Sewage Water Treatment Plant with Capacity 160,000 M3/day in two phases & Reuse for Irrigation, Biogas & Power Production, Mixing with Solid waste for Sludge treatment for fertilizers in 2/3 phases. |
2011 |
2015 |
80 |
Technical & Financial Evaluation of the Process and all components, Review of the preliminary hydraulic Calculation, prequalification of bidders, O&M Offer Review, Evaluation Report. |
Arab Company for Projects and Urban Development |
Egypt |
|
RO Desalination Plant of 25000 M3/D at hurghada |
Design Review & Supervision of Two Seawater RO Desalination Plant at Hurghada of Capacity 5 MIGD SWRO 20,000 M3/D + 5000 M3/D |
2010 |
2012 |
55 |
Bid Evaluation, Assistance to Prepare Contract, Construction Management & Supervision, Design Review, Attending Manufactures Tests, Commissioning |
National Orgnization for Potable Water And Sanitary Drainage(NOPWASD) |
Egypt |
|
Yanbu Independent Water & Power Project IWPP |
1500 MW Steam Generators and Auxiliaries, Steam Turbine, Transformers and HV, MV, LV Electrical System, Fuel Management and Handling, Foundations, Structures, Chimneys, Building and Services, 33 MIGD Desalination, (Two Alternatives MSf and/or RO)Main Pipework System, Product Water Storage and Forwarding |
2008 |
2009 |
1700 |
Preliminary Design Report, Final Tender Document. Evaluation Report, Site Supervision, Guarantee |
E.ON Projects Consultancy LTD |
Saudi Arabia |
|
Consultancy Services for Supply and Installation of Boom at Ghubrah Power and Desalination Plant |
Gather Geotechnical information like tide pattern, water current, wind velocity, depth of seabed from shore to shore at intake, find a permanent boom, prepare detail relevant drawings of boom |
2004 |
2005 |
0.4 |
Preparing Study Report and Prepare scope of work for bidding contractor |
Ministry of Housing Electricity and Water (MHEW) |
Sultanate Of Oman |
|
Richards Bay Desalination Plant 100,000 M3/Day IPWP |
RO Desalination with Diesel power Plant 30 MW |
2010 |
2012 |
200 |
Design, Preparing tender document, Tender analysis, Post contract duties, including design review site supervision of construction and commissioning |
HKS Group |
South Africa |
|
New RO Plant 3.3 USMGD at Dalma Island |
Supply & Installation of 3.3 US MGD SWRO Plant and Addition of 2nd Pass to Existing 2 US MGD SWRO Desalination Plant at Delma Island |
2008 |
2012 |
40 |
Design, preparing Tender Document, Tender Analysis, Post Contract Duties including Design Review, site supervision of construction, commissioning and guarantee period |
Abu Dhabi Distribution Company (ADDC) |
United Arab Emirates UAE |
|
Design and Supervision of Desalination Plant at Al Awaifiya in Wilayat Bahla |
RO DESALINATION PLANT OF 200M3/DAY, Wells, Pretreatment, RO System, Post treatment, Product Water Tank, Civil works, Electrical and I&C System. |
2008 |
2011 |
1.8 |
Study and Design, Tender Document, Bid Evaluation, Assistance to Prepare Contract, Design Review, Construction Supervision, Commissioning, Guarantee Services |
Public Authority for Electricity and Water |
Sultanate Of Oman |
|
Extension Of RO Plant In Qarn Alam |
RO Plant Of 100m3/D With Its Auxiliaries: Drilling Of 2 Bore Wells Pretreatment Facilities, RO Unit With Pressure Exchanger Post Treatment Facilities, PW Tanks, Electrical Supply, Motors, Cables Automatic Control System & Civil Works. |
2008 |
2011 |
1 |
Design Tender Document Evaluation, Site Supervision And Guarantee |
Public Authority for Electricity and Water |
Sultanate Of Oman |
|
Number of projects: 279
|