2x(500-600)MW Power Station with the Associated Transmission System Reinforcements |
|
Description: |
Study the different fuel alternative (including coal) to select the feasible & viable and least cost solution for fuel to build power station 500-600 mw in Aden and Hodeidah, study the impact of adding the power station on the national grid and transmission system reinforcement needed. |
Start Date: |
2013 |
Complation Date: |
2020 |
Cost: |
1200 million US $ |
Services Provided: |
Feasibility study, study
Report, concept design,
Tender document
|
|
|