2x(500-600)MW Power Station with the Associated Transmission System Reinforcements
Description: Study the different fuel alternative (including coal) to select the feasible & viable and least cost solution for fuel to build power station 500-600 mw in Aden and Hodeidah, study the impact of adding the power station on the national grid and transmission system reinforcement needed.
Start Date: 2013
Complation Date: 2020
Cost: 1200 million US $
Services Provided: Feasibility study, study Report, concept design, Tender document